Site Preparation & Installation
-
Install the tank in an upright position, supporting the entire base of the tank on a solid level surface. Ensure that the area is free from sharp stones, iron bars or any debris.
-
The site must be solid, level, compacted base that extends beyond the diameter of the tank. Suitable bases include brick, concrete, gravel with sand top surface between 300mm and 400mm in depth.
-
The site must be solid, level, compacted base that extends beyond the diameter of the tank. Suitable bases include brick, concrete, gravel with sand top surface between 300mm and 400mm in depth.
-
Install the tank in an upright position, supporting the entire base of the tank on a solid level surface. Ensure that the area is free from sharp stones, iron bars or any debris.
-
Leave sufficient space between the tank and any surrounding structures to allow for expansion when the tank is filled. We recommend a minimum of 150mm (6 inches) all around. Position the tank ensuring best access for filling, maintenance and safety.
-